As of Friday, January 11, 2013
© Copyright 2013
Albany Herald
ALBANY, Ga. -- As demolition crews begun work dismantling its trademark arched piers Friday, GDOT officials say the work to tear down and rebuild the Broad Avenue Bridge is about a fifth of the way through, with more than $2.2 million already paid to contractors.
PCL Civil Constructors Inc., of Tampa, has been working to demolish the 90-year-old bridge for more than a month. David Spear, the spokesman for the Georgia Department of Transportation — the lead project manager on the demolition and reconstruction project — said that, as of Dec. 31, workers had completed 19 percent of the total scope of work.
The $11.8 million contract was awarded to PCL after the Albany City Commission agreed to let GDOT move forward with the project over the objections of a local bridge preservation group that had sought consideration to transform the bridge into a pedestrian park.
According to Spear, the project is largely on budget. Two change orders, or “supplemental agreements” in GDOT terminology, have been processed, increasing the budget of the project by $30,000.
One of the change orders, a change in the wall thickness of a gas line pipe that was relocated under the river, was added at no additional cost. The other change order, a study of the riverbed that will help the state and the contractor to avoid leaving any debris behind after construction is complete, increased the budget by $30,700.
Portions of the bridge that had historical significance, including the original plaques that were put on the bridge designating it as a memorial to World War I veterans, were removed before demolition began and are being stored at the Thronateeska Heritage Museum.
More like this story
- Broad Avenue Bridge demolition contract awarded ( May 8, 2012 )
- Tampa company likely to demo Broad Avenue bridge ( April 20, 2012 )
- Bridge group seeks delay on Broad Avenue Bridge demolition until July ( March 1, 2012 )
- Group hopes to save bridge ( November 30, 2011 )
- Group launches online petition to save bridge ( January 31, 2012 )


Comments
Use the comment form below to begin a discussion about this content.
Sign in to comment
Or login with:
OpenID